NEW HOME CONSTRUCTION STEPS & TIMELINE
Mortgage Approval 2 - 4 Weeks Sealed Architectural Plans from 3 - 4 Weeks Factory for Permit All Required Permits to Construct 3 - 4 Weeks Clear Site/Construct Basement 1 - 2 Weeks Shipment of House From Factory 6 - 8 Weeks Set House with Crane & Set Crew 2 - 5 Days Complete Structure on Site 60 - 120 Days COMPLETION TIME FOR CONSTRUCTION WILL VARY DEPENDNG ONTHE SIZE OF THE HOME AND WEATHER CONDITIONS.